Interface risk in construction
Interfaces are points of interaction between two or more aspects of a project:
- Physical interfaces occur where different contractors are engaged on the same project, particularly where their respective works interact or connect in some way.
- Relationship interfaces occur between different stakeholders on a project, such as; contractors, local community groups, regulatory bodies, the client, and so on.
Interface risk, and the failure to manage it effectively, is a common cause for problems on construction projects, giving rise to:
- Delays in completion.
- Claims for damages.
- Stakeholder complaints.
- Loss of profit.
- Industrial action.
- Regulatory infringements.
- Reputational damage.
Managing interface risks between the contracting parties typically involves contractual provisions which might include collaboration and co-operation clauses, clear and complete design documents and specifications, fit for purpose clauses, insurances and warranties, variation clauses and so on.
Interfaces between parties without a contractual relationship can be less straight-forward, but may involve:
- Alliancing and partnering agreements to encourage stakeholders to tackle interfaces early on, and promote a no-blame culture.
- Regular meetings between stakeholders to identify and manage new interfaces.
- Stakeholder mapping and stakeholder management strategies to predict how the project will affect stakeholders and how they can affect the project.
- Identifying and assessing third party dependencies.
It is important that responsibility for managing interfaces is allocated to a specific individual or organisation, as they can often fall between responsibilities or contracts. This is particularly important on large or complex projects where there may be a very large number of interfacing organisations, contracts and packages of work.
New technologies such as Building Information Modelling (BIM) can help identify both soft and hard interface risks, as well as encouraging effective collaboration between stakeholders on a project. Clash avoidance and clash detection should be carried out as an integral part of the design and construction process, from defining standard methods and procedures and establishing a BIM volume strategy, through to specialist design and the creation of a virtual construction model and should continue during the construction phase itself as models are updated with as-constructed information.
[edit] Related articles on Designing Buildings Wiki
- A solution to handle large and complex construction projects: Interface Management.
- Code of practice for project management.
- Conflict of interest.
- Design management.
- Method statement.
- Programme.
- Project manager.
- Receptor.
- Risk assessment.
- Risk in building design and construction.
- Risk management.
- Stakeholders.
Featured articles and news
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.
The story of this knowledge quarter building.
In ecology, in hydrology, in biology and in architecture.
Creating environments that promote physical, mental, and social well-being.
UK cases of neutral current diversion
Research project looks for example contributions.
Overstocking and macro-economics cause a decline.
The 2024 update of the Common Assessment Standard
Demonstrating organisational capability’ to fulfil roles under the Building Safety Act.
56 recommendations for a better built environment
Published by the CIC ahead of the King’s Speech.
SkillELECTRIC Top 8 Competitors Named
in annual search for the UK’s best student electrician.
CIOB Diversity and Inclusion technical information sheet
Step-by-step guide on implementing D and I practices.
Conservation and the Indian City. Book review.
Reversibility in conservation ethics
Learning from painting conservation.
Where It's AT Podcast launched!
New CIAT Architectural Technology Podcast goes live.